Construction30 July 20261 min read
Construction report: July 2026. The next level
Columns of the next level are being erected, and formwork for the next floor slab is being installed.

Photo gallery
Related

Construction
Building A: the frame is up, concrete works continue on the upper floors
The active stage of cast-in-place concrete works on Building A continues at the Wyndham Garden Bucharest Airport site.

Construction
Construction report: October 2026. Works on the upper floor slab
Crews are working on the upper floor slab: installing column reinforcement and preparing the next stage of monolithic works.

Construction
Construction report: September 2026. The frame is rising
The frame of Building A has risen several levels and is clearly visible from the road to the airport. Project banners have been installed around the perimeter of the site.